Automated control system of bulk cement shipping into auto and railway transport


Customer: JSC "Nikolaev Cement Factory", Nikolaev regionControl Object

Hardware / Software: SCHENCK Weighing Transmitters | PLC Siemens S7-300 | Card Terminals Euchner | HMI Siemens OP7 | Profibus-DP | RS-422 | RS-232

Scope of work: central project, installation supervision, commissioning

Year of implementation: 2002


Photomaterials:

System Structure PLC Control Cabinet Control panel of bulk cement shipping


* this project was developed and implemented while working in "CSC-Automation" Vinnitsa Branch Ltd

Standard project includes:

  • Automation Plans
  • Schematic Diagrams (electrical, pneumatic, etc.)
  • Connection Diagrams and External Wiring Connections
  • Drawings of Equipment and External Wiring Location
  • Specification of Equipment and Materials
  • Estimates for Installation, Commissioning etc.
  • Documentation for Control Cabinets and Operating Consoles
  • PLC and SCADA Software
  • Operation and maintenance documentation (including operator manuals, instructions for maintenance, software and hardware description etc.)